浅谈大型机电设备安装与调试§

【摘要】本文根据笔者多年机电设备安装实践经验,从电动机调试起动前、运行过程、故障

原因诸多细节检查人手,详细介绍了大型机电设备安装调试过程中过程中经常出现或者
有可能出现的问题,并以典型回路为例,具体分析阐述了电动机起动失效的原因及解决
办法,并就电动机运行过程中的监视与维护进行了扼要说明,供同行参考。
【关键词】电动机;安装调试;故障;控制与保护
【 Abstract】 This text according to the writer several years machine electricity the equipments 
install   fulfillment   experience,   from   the   electric   motor   adjust   before   trying   to   start,   circulate 
process,   break   down   reason   many   detail   check   hand,   detailed   introduction   large   machine 
electricity   equipments   install   adjust   to   try   process   in   in   the   process   usually   appear   perhaps 
probably appear of problem, and take typical model back track as an example, concrete analysis 
elaborated electric motor to start expiration of reason and solution, and electric motor circulate 
process in of surveillance and maintenance carry on concise elucidation, is provided to go together 
reference.
【Key words】Electric motor;Install to adjust to try;Break down;Control and protection
1. 概述
在工程机电设备安装施工完成之后,通常要对电动机及其所带的机械作单机起动调试。调
试运行设备是在施工单位人员的操作下,按照正式生产或使用的条件和要求进行较长时
间的工作运转,与项目设计的要求进行对比。目的是考验设备设计、制造和安装调试的质
量,验证设备连续工作的可能性,对设备性能作一检测,并将检测的数据与设备制造出
了记录的数据进行比较,对设备工程的质量作出评价。在实际工作中设备的试运行往往会
碰到意想不到的异常现象,使电动机起动失败而跳闸,较大容量的电动机机会便多一些。
为了便于事后分析,而电机起动之前,我们就应做好事前准备工作(尤其是大型电动机更
需要重视),并对检查的结果加以分析。
2. 电动机起动前的检查与试运行检查
    2.1 启动前的检查。
    2.1.1 新安装的或停用三个月以上的电动机,用兆欧表测量电动机各项绕组之间及每项
绕组与地(机壳)之间的绝缘电阻,测试前应拆除电动机出线端子上的所有外部接线。通常
对 500V 以下的电动机用 500V

 

兆 。

    欧表测量,对 500~3000V 电动机用 1000V 兆欧表测量其绝缘电阻。按要求,电动机每
1KV 工作电压,绝缘电阻不得低于 1MB·Ω,电压在 1kV 以下、容量为了 1000KW 及以下
的电动机,其绝缘电阻应不低于 0.5MB·Ω。如绝缘电阻较低,则应先将电动机进行烘干处
理,然后再测绝缘电阻,合格后才通电使用。
    2.1.2 检查二次回路接线是否正确,二次回路接线检查可以在未接电动机情况下先模拟
动作一次,确认各环节动作无误,包括信号灯显示正确与否。检查电动机引出线的连接是
否正确,相序和旋转方向是否符合要求,接地或接零是否良好,导线截面积是否符合要
求。
    2.1.3 检查电动机内部有无杂物,用干燥、清洁的 200~300KPa 的压缩空气吹净内部(可使
用电吹风机或手风箱等来吹),但不能碰坏绕组。
    2.1.4 检查电动机铭牌所示电压,频率与所接电源电压、频率是否相符,电源电压是否稳
定(通常允许电源电压波动范围为±5%),接法是否与铭牌所示相同。如果是降压起动,还
要检查起动设备的接线是否正确。