杭瑞高速公路(贵州境)遵义至毕节段新建设工程实施性施工组织设计
22 合同段
..................................................................................
..........................................................................................
......................................................................................
.....................................................................
......................................................................................
......................................................................................
......................................................................................
..........................................................................
..........................................................................................
......................................................................................
..........................................................................................
..................................................................................
..........................................................................................
表
5 主要分项工程施工工艺框图
1 石 方 路 堑 开 挖 施 工 工 艺 框 图 ( 见 表 5-
1 )
1.1施工准备:测量放样,清除非适用材料,机械开挖爆破工作平台。
1.2 机械钻孔:采用潜孔钻机分台阶平行钻孔施工,钻孔倾斜度按 75°控制
孔深根据需要在
4 ~ 8m之间。
1.3清孔装药:采用空压机送风清孔,爆破工按设计的结构形式装药,每人
安装一种段别的微差雷管及导爆索,上部用黄泥封孔。
1
中铁十七局集团第一工程有限公司遵毕高速公路 22 合同段项目经理部