建筑幕墙施工技术质量监理控制探讨

  摘要:随着幕墙的高速发展,监理对幕墙的质量控制也越来越显得至关重要。由于幕
墙工程的特殊性,其质量监理要依靠事前控制和事中控制为主,因此,监理人员必须全
面详细地熟悉整个施工工艺流程,事先提出质量控制和检验标准,监督施工单位严格遵

 

守和执行,从而达到预期的质量控制目标。

 

  关键词:建筑幕墙;施工技术;质量控制;监理;探讨
   Abstract: with the rapid development of curtain wall, supervision of the quality control of 
curtain wall also appears more and more vital. Because of the particularity of curtain wall project, 
its quality supervision to rely on beforehand control and course control primarily, therefore, the 
inspection personnel must be fully detailed familiar with the whole construction process, proposed 
the quality control in advance and inspection standard, supervision and construction unit strictly 
abide by and implementation, so as to achieve the anticipated quality control goals. 
    Keywords:   the   construction   curtain   wall;   Construction   technology;   Quality   control; 
Supervision; explore

 

  

 

  
  随着我国国民经济的高速发展和人民生活水平的不断提高,建筑物越来越向高层、高
档、多功能方向发展。由于建筑幕墙是在宅外高宅的装饰形式,其施工质量直接影响安全。
因此必须更加严格地监理其施工过程,才能保证工程质量。结合监理实践,谈一些对建筑

 

幕墙质量监理的体会和看法。

 

  

 

 

  一 建筑幕墙施工监理要点分析

 

  (一)编制监理细则。根据工程验收规范和实际要求,编制可行的监理实施细则。
  (二)体系审查。开工前,应审查施工单位现场项目管理机构的质量管理体系、技术
管理体系和质量保证体系,审查承建单位的资格、技术与管理水平、以往的施工业绩、特殊

 

工种人员上岗证书等。
  (三)审查施工组织设计。监理人员应重点审核施工方案、施工机械及施工顺序,尤
其是关键工序的工程质量控制及保证措施,主要包括安装工序、安装机具和工具、脚手架、
铁码和预埋件连接、立柱与横梁安装及位置调整、焊接防锈措施、板材安装、防火棉安装、防

 

雷系统安装、铝框和玻璃保护等。
  (四)图纸会审及设计交底。施工单位根据效果图及框架实际几何尺寸出施工图及集
点大样图和结构计算书,须经业主、设计确认,再进行图纸会审。图纸会审重点:图纸是
否符合技术规范要求;设计是否满足安全、合理、技术先进的原则;设计是否满足建设单
位要求;施工是否方便、合理、节约;对重点部位的设计意图、技术要求、难点及质保措施,

 

向施工单位作技术交底。
  (五)审查进场原材料。为使建筑幕墙工程安全可靠,幕墙材料应该符合设计要求及
国家现行产品标准和工程技术规范的规定。为使建筑幕墙有足够的耐候性和耐久性,要求
建筑幕墙所用金属材料除不锈钢和轻金属材料外均应进行热镀锌防腐处理,铝合金应进

 

行表面阳极氧化处理。
  (六)加工制作、施工安装前条件检查复核。幕墙在制作前对建筑设计施工图进行核
对,并对已建建筑物进行复测,按实测结果对幕墙调整并经设计、监理同意后,方可加工
组装。为保证幕墙质量,要求主体结构工程应满足幕墙安装的基本条件,特别是主体结构
的垂直度和外表面平整度及结构的尺寸偏差,必须达到钢筋 NT 结构施工及验收规范要