background image

青岛理工大学毕业设计(论文)

ABSTRACT

This  graduation  project  is  designed  for  the  factory  transformer  substation,  to 

certain questions in factory transformer substation design: the load computation, the 

analysis of three-phase short-circuits, the short-circuit current computation, the choice

and verification of high and low pressure equipment, the transformer relay protection, 

the  secondary  circuit  of  the  transformer  substation  and  the  automatic  device,  anti-

thunder  and  the  connection  to  the  earth,  the  transformer  substation  overvoltage 

protection,  the  measurement,  the  idle  work  compensated  and  so  on,  All  the  above 

aspects and the structure of the power supply host wiring topology have been stated.

The  transformer  substation  with  a  10kV  single  power  source  coil  in  it  uses 

1600kVA main transformer, the biggest computation shoulders of which is 1636kW.It 

adopts the shunted capacitor to carry on the low pressure centralism for compensation 

and sets protection for the transformer by carring on the electric current to it breaking 

the  speed  of  the  flow  gas  protection,  garrisons  accerding  to  the  third  kind  of  anti-

thunder  buildings,and  users  the  strong  and  weak  electricity  union  earth  system  to 

carry on the protection to the building.

Based  on  the  computation  of  short-circuits  to  the  power  supply  system,  the 

project  has  a  choice  design  of  the  power  cable  and  the  electrical  equioment  and  a 

preliminary design to the outdoors plane arrangement at the same time.

Keywords

 : the power distribution ,supply in factory,the relay protection

II